Selective Demolition & Excavation
• Sawcut and remove existing 4" unreinforced concrete basement slab (approx. 1,450 sq.ft) with electric or hydraulic saws to prevent CO toxicity indoors.
• Excavate basement floor to an average depth of 28 inches below existing floor elevation to achieve target 8'-6" clear basement ceiling height.
• Install temporary structural shoring posts and jacks supporting the existing 2-storey floor system prior to load-bearing partition demolition.
Structural Underpinning (1-2-3 / A-B-C Sequence)
• Sequentially excavate and cast 31 reinforced concrete underpinning pins around exterior foundation perimeter in strictly alternating sequence (Section 1, 2, 3 or A, B, C).
• No adjacent pins shall be excavated simultaneously. Concrete shall cure for a minimum of 48 hours prior to dry-packing.
• Place minimum 2" to 3" non-shrink structural dry-pack grout (min 50 MPa at 28 days) rammed between top of cured underpinning concrete and underside of existing rubble/concrete footing.
Cast-In-Place Concrete & Moisture Protection
• Supply and install interior 4" perforated weeping tile connected to existing or proposed sump pit, covered with 3/4" clear stone wrapped in filter geotextile.
• Install 10-mil polyethylene or 2" extruded polystyrene (XPS R-10) continuous sub-slab vapor barrier taped at all laps.
• Pour new 4" concrete basement slab with 25 MPa compressive strength, 5-7% air entrainment, smooth steel-troweled finish.
Subcontractor Tender Pricing (4 Norlong Blvd)
Target Budget Benchmark: $105,000 CAD| Subcontractor Name | Demolition (1,450 SF) | Underpinning (31 Pins) | Concrete Works | Total Bid (CAD) | Status / Action |
|---|---|---|---|---|---|
|
Apex Shoring & Foundation Inc.
WSIB & Tarion Registered
|
$14,500 ($10/SF) | $69,750 ($2,250/pin) | $18,850 | $103,100 | |
|
GTA Underpinning Solutions
5M Liability Insurance
|
$17,400 ($12/SF) | $72,850 ($2,350/pin) | $19,500 | $109,750 | Under Review |
|
Toronto Basements & Concrete Ltd.
Standard Bonded
|
$18,850 ($13/SF) | $77,500 ($2,500/pin) | $21,000 | $117,350 | Over Budget |
Client Project Dashboard: 4 Norlong Blvd
High-level construction progress, permits, and financial approvals.
Key Stages & Structural Safety Sign-Offs
Removal of old basement floor slab and earth excavation to create 8'-6" finished ceiling height.
Poured in small alternating segments so the house always remains securely supported on undisturbed ground.
New vapor barrier, interior weeping tile system, and 4" smooth concrete slab.
Subcontractor Tender Submission: 4 Norlong Blvd
Review verified takeoff quantities, enter your company unit rates, and submit your formal bid.